Project
Overview
Basic
facts
Pipeline
route
Map
of route
Special
lands consideration
Local
economic impact
Basic
Facts
The project
involves burying a 24-inch wide pipe about 3-5
feet underground along a 77-mile route that runs
from Victor, NY, to Corning, NY. As a safety precaution,
markers will be placed at points along the pipeline
route. Construction involves digging a trench
4-5 feet wide at ground level. To build the pipeline,
Empire will secure a right-of-way of about 75-100
feet during construction. The right-of-way will
be reduced to about 50 feet after construction
is completed. Pipeline construction on a 20 –
25 mile portion of the project will begin on September
17, 2007, and will conclude by early December.
The remainder of the pipeline will be constructed
beginning in the spring of 2008 and will be completed
in the fall of 2008. The Compressor Station (which
will be located in Oakfield, NY) will also be
constructed in 2008. Click here for route maps, which include the areas to be impacted by pipeline construction in 2007 and 2008. The maps outline the route as it impacts each county affected.
Pipeline
Route
In December
2006, FERC granted the Empire Connector Project
a Certificate of Public Convenience and Necessity,
thereby granting approval to construct and operate
the natural gas pipeline.
Thanks to the exceptional cooperation of property
owners, Empire Pipeline was granted access to
more than 94% of the route area to complete survey
work during the project’s development. Surveyors
were able to identify special areas of concern
and sensitivity along the initial primary route
and made a number of adjustments to the route
plan. In some cases, the areas now considered
as the best route were originally a secondary
alternative; in other areas, a new route configuration
was developed.
Click
here to download the route map, in pdf format.
Special
Land Considerations
The Empire Connector is designed
to minimize the impact to agricultural and recreational
lands affected by the final route. Recreational
lands may be disturbed during the construction
period but will be returned to original or better
condition. Agricultural lands affected by the
final route will be properly restored using approved,
modern mitigation techniques designed to ensure
full productive reuse of the agricultural lands.
For
more information about the pipeline and agricultural
areas, click here.
Local
Economic Impact
The
total cost of the Empire Connector Project is
roughly $ 177 million. Municipalities stand to
directly benefit from this project. The pipeline
will generate millions of dollars in new tax payments
for schools, local governments and the state.
Several
hundred temporary construction jobs will be created
during the construction period, which will last
approximately 6-9 months. During that time, additional
economic activity for businesses near the pipeline
route is expected. Click
here to learn more about the economic benefits
of the Empire Connector.
Project
Timeline
|
Project
Timeline |
|
| September
2004
|
Public
meetings were held throughout the proposed
pipeline area |
| Sept.
– Dec. 2004
|
Initial
surveying of land is completed |
| Dec.
2004
|
Public
Meeting for the Compressor Station was
held |
| October
2005
|
Empire
Connector’s application is filed
with FERC |
| Fall
2006
|
Requested
date for FERC to provide its determination
on the Empire Connector |
| November
2006
|
Held
meeting for farmers regarding monitoring,
inspection and mitigation techniques |
| December
2006 |
FERC
granted Empire the approval to construct
and operate the pipeline |
| September 2007-May 2008 |
Final surveying and right of way negotiations |
| September 17, 2007 |
Pipeline construction begins on a section of the pipeline in Yates and Schuyler Counties |
| December 2007 |
Construction on 18 miles of the pipeline completed |
| Winter 2007 – Early 2008 |
Applicable preparation work for spring construction |
| May 2008 |
• |
Pipeline construction begins on remainder of route and compressor station as weather allows |
• |
Clearing and road boring begins |
|
| November 2008 |
In-service date |
| Summer 2008, 2009 and ongoing |
Restoration followed by crop monitoring |
|
|