Go to the National Fuel Gas homepage
Building on 100 Years...Delivering Energy
     

Project Overview

  ABOUT EMPIRE CONNECTOR
  PROJECT OVERVIEW
 

PROJECT ROUTE

 

ROUTE MAPS

 

PROJECT TIMELINE

  FOR LANDOWNERS
  FOR FARMERS
  FOR POTENTIAL PIPELINE CUSTOMERS
  COMPRESSOR STATION
  REGULATION, ENVIRONMENT AND SAFETY
  PUBLIC MEETINGS
  FREQUENTLY ASKED QUESTIONS
  NEWS RELEASES
  QUESTIONS, COMMENTS AND INPUT
  DOCUMENTS
  USEFUL LINKS
  CONTACT INFORMATION
 

 

Project Overview

Basic facts

Pipeline route

Map of route

Special lands consideration

Local economic impact

Basic Facts

The project involves burying a 24-inch wide pipe about 3-5 feet underground along a 77-mile route that runs from Victor, NY, to Corning, NY. As a safety precaution, markers will be placed at points along the pipeline route. Construction involves digging a trench 4-5 feet wide at ground level. To build the pipeline, Empire will secure a right-of-way of about 75-100 feet during construction. The right-of-way will be reduced to about 50 feet after construction is completed. Pipeline construction on a 20 – 25 mile portion of the project will begin on September 17, 2007, and will conclude by early December. The remainder of the pipeline will be constructed beginning in the spring of 2008 and will be completed in the fall of 2008. The Compressor Station (which will be located in Oakfield, NY) will also be constructed in 2008. Click here for route maps, which include the areas to be impacted by pipeline construction in 2007 and 2008. The maps outline the route as it impacts each county affected.

 

Pipeline Route 

 

In December 2006, FERC granted the Empire Connector Project a Certificate of Public Convenience and Necessity, thereby granting approval to construct and operate the natural gas pipeline.

Thanks to the exceptional cooperation of property owners, Empire Pipeline was granted access to more than 94% of the route area to complete survey work during the project’s development. Surveyors were able to identify special areas of concern and sensitivity along the initial primary route and made a number of adjustments to the route plan. In some cases, the areas now considered as the best route were originally a secondary alternative; in other areas, a new route configuration was developed. Click here to download the route map, in pdf format.

Special Land Considerations

The Empire Connector is designed to minimize the impact to agricultural and recreational lands affected by the final route. Recreational lands may be disturbed during the construction period but will be returned to original or better condition. Agricultural lands affected by the final route will be properly restored using approved, modern mitigation techniques designed to ensure full productive reuse of the agricultural lands.

For more information about the pipeline and agricultural areas, click here.

Local Economic Impact

The total cost of the Empire Connector Project is roughly $ 177 million. Municipalities stand to directly benefit from this project. The pipeline will generate millions of dollars in new tax payments for schools, local governments and the state.  

 

Several hundred temporary construction jobs will be created during the construction period, which will last approximately 6-9 months. During that time, additional economic activity for businesses near the pipeline route is expected. Click here to learn more about the economic benefits of the Empire Connector.

Project Timeline

Project Timeline
September 2004 Public meetings were held throughout the proposed pipeline area
Sept. – Dec. 2004 Initial surveying of land is completed
Dec. 2004 Public Meeting for the Compressor Station was held
October 2005 Empire Connector’s application is filed with FERC
Fall 2006 Requested date for FERC to provide its determination on the Empire Connector
November 2006 Held meeting for farmers regarding monitoring, inspection and mitigation techniques

December 2006

FERC granted Empire the approval to construct and operate the pipeline
September 2007-May 2008
Final surveying and right of way negotiations
September 17, 2007 Pipeline construction begins on a section of the pipeline in Yates and Schuyler Counties
December 2007 Construction on 18 miles of the pipeline completed
Winter 2007 – Early 2008 Applicable preparation work for spring construction
May 2008
Pipeline construction begins on remainder of route and compressor station as weather allows
Clearing and road boring begins
November 2008 In-service date
Summer 2008, 2009 and ongoing Restoration followed by crop monitoring

 

 

 


Privacy Policy
| Terms and Conditions| Disclosures Regarding Forward-Looking Statements | Search | Home

© 1996- National Fuel Gas Company