For
Landowners
Latest
News
Fast Facts
How landowners will be contacted
Survey
Process
Compensation for right-of-way
Latest
News
Recent project developments include: completion of the first phase of pipeline construction by building 18 miles of the Empire Connector in Yates and Schuyler counties; completion of the kick-off construction meetings held in Watkins Glen, Canandaigua and Victor; and finalizing the project’s construction schedule of pipeline construction slated to begin this spring. Click
here for more information.
Fast
Facts
- Property
owners identified as having property that will
be impacted by the pipeline will be offered
fair compensation
for a permanent right-of-way agreement and any
temporary economic loss caused by construction.
- Historically, the presence of a natural gas
pipeline has not negatively impacted property
values.
- Recreational lands may be disturbed during
the construction period, but will be returned
to original, or better, condition.
- Agricultural
lands affected by the final route will be properly
restored using modern, approved mitigation techniques
designed to ensure full productive reuse of
the property.
- The
Federal Energy Regulatory Commission’s
website contains helpful information for landowners
about citizen
involvement and citizen rights. The website
also has information regarding the approval
process for the project.
How
landowners will be contacted
Landowners along the proposed
route will be kept informed about all aspects
of the project that may impact their property,
including the dates for public meetings, surveying
in their area, right-of-way negotiation and project
developments. To view the letters sent to landowners,
beginning with the project announcement in 2004,
click here.
Empire Pipeline will also keep property owners up to date on project activities through Empire Connections, the official newsletter of the Empire Connector Project, developed exclusively for property owners affected by the project. Property owners received the first edition in March 2005, a second edition of the newsletter was issued in November 2005 and a third edition was issued in April 2008.
If
you would like to receive email alerts about developments
in the project, click
here to have your email added to the recipient
list.
Surveying
substantially complete
Most of the surveying along the route was completed
in the fall of 2004, the summer of 2005 and during
spring of 2006. Empire Pipeline was able to make
great progress on this phase of the project thanks
to the extraordinary cooperation it received from
landowners.
The input gathered from property owners and the
identification of areas of special concern and
sensitivity led to a number of adjustments being
made to the route plan.
A
map of the route is available. Click
here to download the approved route map in pdf
format.
Survey
process
Surveyors collected important data and assessed
environmental, geological, and archeological conditions.
This process also included considerable interaction
with property owners along the proposed route
so that their concerns could be assessed and,
in many cases, become part of route plan modifications.
Compensation
for right-of-way
Identified landowners will
be offered fair compensation for a permanent right-of-way
agreement and any temporary economic losses caused
by the project’s construction. Land disturbed
during construction will be restored to original,
or improved, condition.
Right-of-way negotiations began in spring 2007,
with representatives visiting landowners to negotiate
right-of-way agreements and discuss right-of-way
compensation. Landowners should let those representatives
know of any special land considerations or concerns.
Right-of-way compensation is determined by the
current land use and is based on current land
values established by recent sales of comparable
properties in the area.
Construction
to start in September 2007
After completing development work and receiving,
on December 21, 2006, the Federal Energy Regulatory
Commission’s (FERC) approval to construct
and operate the Empire Connector, construction
of the pipeline will begin on September 17, 2007,
on a 20 – 25 mile stretch of the pipeline
route click here for
a route map, including a map of the 2007 construction
area. For most of the project area, pipeline construction
will not begin until spring of 2008. However,
in certain areas, selected road and waterway crossings
and other preparatory work will be completed in
2007 and early 2008.
The area identified for pipeline construction
is in Yates and Schuyler counties, beginning just
north of the Keuka Outlet, and concluding at County
Road 16, just east of its intersection with Townsend
Road. Starting on September 17, 2007, crews will
be working in the pipeline construction area to
clear the workspace. All of the construction planned
for this portion of the project was completed in December 2007. Work on the second phase of the construction project began in May 2008.
Local
contractor selected
A local firm, Otis Eastern Service Inc. was selected
as pipeline construction contractor. Based in
Wellsville, N.Y., Otis Eastern is one of the leading
pipeline contractors in the United States and
has deep experience in constructing pipelines
in New York State and, particularly, through agricultural
lands. Otis Eastern has completed other pipeline
work for National Fuel in the past and the Company
has great confidence in Otis Eastern’s ability
and experience. It was imperative that this important
work is entrusted to a reputable and experienced
contractor who shares the company’s philosophy
of reducing the impact to landowners along the
route by keeping safety, timeliness and environmentally
sound construction practices as top priorities.
Oversight
of construction
Along with Otis Eastern, which has the highest
standards for construction and safety, this project
will be carefully and thoroughly scrutinized.
In this case, approximately 20 trained and experienced
inspectors will be in the field, monitoring the
construction activities. Click
here for an organizational chart of the inspection
and monitoring functions.
Of those field inspectors, there will be two
third-party monitors who will report directly
to regulatory agencies (including FERC, the Department
of Environmental Conservation and the Army Corps
of Engineers) and will ensure that the construction
is being completed in a manner consistent with
all environmental and agricultural requirements.
You may talk with any of the field personnel at
any time if you have a question or concern. Moreover,
a project representative will be available to
landowners at any time, to address questions or
concerns related to the construction activities.
An overview
of construction:
Construction Process Step 1: Clearing
and Grading
Prior to the start of construction, a crew will
survey and mark the construction right-of-way
to make sure that the pre-approved construction
workspace is cleared.
Our project will be broken into manageable lengths called “spreads,” which utilize specialized and qualified work groups. To view a map of the 2008 construction zone, click
here.
This crew removes trees, boulders and debris
from the construction right-of-way and prepare
a level work surface for the needed heavy construction
equipment. This can make for a somewhat disruptive,
loud and dusty work zone.

If necessary, the crew also installs silt fencing
along streams and outside wetlands to prevent
erosion of soil disturbed by construction. Trees
inside the right-of-way are removed and the contractor
takes away or stacks the timber along the side
of the right-of-way, depending on the landowner’s
preference.
Customized agricultural mitigation procedures
have been developed and Empire is required to
follow those procedures during construction as
a condition of its FERC certificate. To learn
more about the special provisions for agricultural
lands, click here.
Construction Process Step 2: Trenching
The next step in the construction process is
called “trenching,” which is simply
digging the trench that will contain the pipeline.
The trenching crew typically uses a wheel trencher
or backhoe to dig the pipe trench. The Department
of Transportation requires the top of a pipeline
to be buried at least 3 feet below restored surface
of the ground, and a minimum of 4 feet below in
agricultural lands. The pipeline will be buried
even deeper at river and road crossings and to
accommodate certain other conditions.
In agricultural areas, the topsoil removed is
kept separate from the excavated subsoil, a process
called “topsoiling.” When backfilling
operations begin, after the pipe is installed,
welded, tested and inspected, the soil is returned
to the trench in reverse order. The subsoil will
be put back first, followed by the topsoil, ensuring
the topsoil is returned to its original position.
Construction Process Step 3: Pipe Bending
Bending the Pipe Next, the pipe
bending crew uses a hydraulic machine to make
slight bends in the pipe to account for changes
in the pipeline route and to conform to the topography.
The bending machine uses a series of clamps and
hydraulic pressure to make smooth, controlled
bends in the pipe. All bending is performed in
strict accordance with federally proscribed standards
to preserve the integrity of the pipe.

Stringing, Welding and Coating the Pipe
The sections of pipe to be used to construct
the Empire Connector will be separated into segments
typically 40 to 80 feet long. A “stringing
crew” uses specialized trailers to move
the pipe from a storage yard to the pipeline right-of-way.
The crew monitors the pipeline design plan to
be certain various pipeline segments are distributed
according to specifications along the pipeline
right-of-way. This is because the type of coating
and the pipe’s wall thickness can vary based
on soil conditions and location. Concrete coating
may be used in streams and wetlands, for instance,
and heavy wall pipe is required at road crossings
and in special construction areas.
Construction Process Step 4: Welding
Welding joins sections of pipe into one continuous
length. Special pipeline equipment called a side
boom is used to pick up each pipeline segment
and align it with the previous and ensuing segment.
The crew then makes the first weld. The welding
crew follows the pipeline along the route until
each segment is welded. Depending on the thickness
of the pipe, several passes may be required to
complete each segment weld.
As a safety measure, welds completed during the
construction of the Empire Connector Project are
visually inspected and 100% x-rayed.

Construction Process Step 5: Coating
Pipe
Natural gas pipelines are externally coated at
the factory to prevent moisture from directly
contacting the steel and causing corrosion.
However, all coated pipelines are delivered with
uncoated areas three to six inches from each end
to prevent the coating from interfering with the
welding process.
After the welds are completed, a coating crew
will coat the remaining portion of the pipe before
lowering it into the trench. Prior to lowering
the pipe, the coating on each section of pipe
and the welded areas will be inspected to ensure
it is free of defects.
Construction Process Step 6: Lowering
the Pipeline
With the pipe approved for burial, lowering the
welded pipe into the trench demands close coordination
and skilled operators.
By using a series of side-booms, the welded pipe
sections will be simultaneously lifted and carefully
lowered into the trench. Non-metallic slings protect
the pipe and coating as it is lifted and moved
into position.
In rocky areas, a protective wrap known as “rockshield”
is used to protect the pipe and coating.

Construction Process Step 7: Backfilling
After the pipeline is successfully laid in the
trench, crews will backfill the trench. This can
be accomplished with either a backhoe or padding
machine, depending on the soil’s composition.
The backfilling crew will take care to protect
the pipeline and coating as the soil is returned
to the trench.
Soil will be returned in reverse order, with
the subsoil put back first, followed by the topsoil.
In areas where the ground is rocky, crews will
screen the backfill to remove rocks. If necessary,
they will also bring in clean soil to cover the
pipeline, or cover the pipe with a protective
material to protect it from sharp rocks.
Construction Process Step 8: Testing
Before the Empire Connector Project becomes operational,
the entire length of it will be pressure tested
using water.
Requirements for this test are prescribed in
DOT’s regulations. The pipeline will be
filled with water and pressured to a level higher
than the maximum pressure the pipeline will operate
at when transporting natural gas.
The test pressure will be held for a specific
time to determine if the pipeline meets the design
strength requirements and if any leaks are present.
Once the pipe successfully passes the hydrostatic
test, water will be emptied and the pipeline will
be dried to ensure that no water is present when
natural gas begins to flow.
This hydrostatic testing is the final quality
assurance test before the pipeline is cleared
by inspectors for operation.
Construction Process Step 9: Right-of-Way
Restoration
The final step in the construction process is
to restore the right-of-way to its original or
better condition.
This process involves replacing topsoil, removing
large rocks that may have been brought to the
surface during trenching, completing any final
repairs to existing irrigation systems or drain
tiles, spreading lime or fertilizer, and restoring
fences.
The Empire Connector Project has developed special
procedures for construction and restoration in
agricultural lands. Click
here for more information.
|